The work consists of the installation of approximately 420m of PVC pipe up to 900mm dia., 270m of HDPE pipe up to 762mm dia., 109m of 762mm dia. HDPE pipe bursting, storm system, trailway, asphalt paving and all other work incidental thereto.

The area of work is in the Butterrubs Marsh and requires dewatering and shoring in the southern section.

PROJECT KEY FEATURES:
■ Dewatering Work
■ Traffic Management
■ Environmentally Sensitive Work
■ Pipeline Work
♦ PVC Pipes
♦ HDPE Pipes
■ Municipal Infrastructure Work
♦ Sanitary Sewer
♦ Road Works
■ Shoring Work

VALUE: $3,100,000
LOCATION: Nanaimo, BC
START DATE: April, 2016 END DATE: December, 2016

OWNER: City of Nanaimo