4 land roadway reconstruction for the City of Fort St. John
The reconstruction of 100 Street in Fort St. John included 400m of road including traffic signal, LED streetlighting, storm sewer, multi-use trail and landscaping. 370m of storm sewer c/w out and energy dissipater to Fish Creek.
PROJECT KEY FEATURES:
■ Traffic Management
■ Public/Urban Impact Management
■ Road Building Work
■ Municipal Infrastructure Work
♦ Storm Sewer
♦ Electrical
■ Traffic Signalization Work
VALUE: $5,800,000
LOCATION: Fort St. John, BC
START DATE: May, 2019 END DATE: November, 2019
OWNER: City of Fort St. John