Replacement and installation of water system appurtenances
· 4 x remove and replace hydrant assemblies,
· 1 x new hydrant assembly location,
· 1 x locate existing service
· 1 x locate and replace existing service,
· 8 x mainline valves (150mm and 200mm)
PROJECT KEY FEATURES:
■ Municipal Infrastructure Work
♦ Water Works
■ Traffic Management
VALUE: $450,000
LOCATION: Hudson’s Hope, BC
START DATE: September, 2019 END DATE: October, 2019
OWNER: District of Hudson’s Hope